Site Visit to the 154kV Seonsan to Goa Temporary Transmission Line Relocation Project - Emphasis on Site Safety and Rigorous Quality Management
On September 16, TechBank CEO Kim Yong Bong and other executives from the head office visited the site of the 154kV Seonsan to Goa Temporary Transmission Line Relocation Project, where TechBank is providing construction supervision services.
The visit was organized as part of TechBank’s site focused management approach and to recognize the dedication of employees who are working to ensure rigorous construction quality and thorough safety supervision under the high risk conditions associated with the relocation of a high voltage transmission line. The visit also provided an opportunity to review the overall status of the supervision services being carried out to establish a stable power supply infrastructure and to strengthen technical support and communication between the head office and the project site.
■ Review of Construction Progress and Technical Inspection Activities
During the visit, CEO Kim Yong Bong and the head office executives received a briefing from the chief supervising engineer on construction progress, key technical activities, and occupational safety and health management. They also reviewed major issues arising during the suprevision process and discussed key technial matters requiring attention.
■ Review of Safety Management Procedures and Key Issues
Particular attention was given to the site’s step by step management procedures, including toolbox meetings and alcohol testing before work, on site inspections during work, and confirmation of safe departure after work. The executives also reviewed key issues related to compensation for land affected by the transmission line and instructed the site team to implement necessary improvements.
Through this review TechBank reaffirmed its commitment to continuously strengthening safety management at a high risk construction site and ensuring close coordination between the head office and the project site in addressing major issues.
■ On Site Inspection and Listening to the Supervision Team
Following the briefing, the executive toured the construction site, where foundation work for transmission towers, including micropile drilling and grouting, was underway, and directly inspected the quality of the ongoing work. They also reviewed key work activities with site personnel and took time to listen to the concerns and feedback of members of the supervision team.
■ Emphasis on Rigorous Quality and Safety Management for a Zero Accident Site
CEO Kim Yong Bong emphasized, “For a 154kV high voltage transmission line project, thorough supervision and strict compliance with safety procedures are of utmost importance. I ask everyone to carry our their responsibilities with a strong sense of accountability so that we can meet the trust of our clients, including the Korea Water Resources Corporation and Korea Electric Power Corporation, and achieve a zero accident site through completion.
TechBank will continue to provide high quality power infrastructure supervision services to meet client expectations and provide active technical support from the head office until the successful completion of the project.
2026.09.29